17.1 Flood management
17.1.1 DC800 flooding and other investigations
The 2001 Australia Day weekend rainfall event caused
flooding in the DC800 catchment. This occurred at a time when transmission
flows of 300 ML per day were occurring in DC800 for DLWC to supplement the
Yanco Creek. Rainfalls of around 75 mm, with some readings of up to 100 mm,
were recorded on farms in the DC800 catchment over that weekend. The results of
these combined flows were that the drains quickly filled, water back-flooded up
farm drainage inlets, growing crops were flood-affected and drain-off times
from farms were extended significantly.
As reported in the past two AERs the full length of DC800
from Bridge Road to the Yanco Creek has been cleaned out to reduce flooding. If
this work had not been carried out the 2001 Australia Day weekend flooding
event would have been significantly more serious.
Measures being taken to reduce the effects of flooding in
DC800 include:
- Planned
capital expenditure to automate regulators at the top of Bundure Main so
that big flows can be cut out quickly following rainfall cutbacks.
- Planned
installation of Supervisory Control and Data Acquisition (SCADA) on more
escapes.
- Negotiations
with DLWC to limit the size of diversions down DC800.
- Request
to DLWC to fast-track automation of Tombullen Inlet so that water can be
quickly cut out of the Main Canal.
- Flap
valves to be installed on the downstream end of drainage inlets where back
flooding occurred.
- Investigations
are continuing into reducing restrictions in flow along DC800,
particularly restrictions caused by piers of bridges.
- Investigations
are continuing into alternative ways of conveying water to the Yanco
Creek, given that suitable cost recovery can be agreed.
17.1.2 Flood control works
The siphon under the Main Canal downstream of Tubbo Wells
Escape was cleaned out with specialized high pressure jetting and suction
equipment. The flood control levee
banks were inspected.