14.1 Seepage control works
Seepage investigations in the CIA during 2000/2001 consisted
of the examination of two km of EM-31 data for the Boona Main Supply Channel at
the Eastern end of Bull Road. Seepage
investigation techniques are now being applied on-farm to assist shareholders
in identifying farm channel seepage problems.
Seepage treatment works carried out in the CIA (see below)
include clay re-lining of banks, bank reconstruction and bank and bed
reconstruction.
- A 400m
section of the left bank of Yamma 2 Supply Channel upstream of Kidman Way
was re-lined with clay. Due to
high accession to the groundwater through the bed of the channel at this
location, 325m of bed re-lining was necessary.
- A 400m
section of the left bank of Bundure 3 Supply Channel was reconstructed at
Farm 606. The presence of soil with a high content of gypsum shot
necessitated the re-lining of 400m of the bed of this channel as
well.
- A 50m
section of both banks and the bed of the Argoon 3 Supply Channel were re-lined
with clay. The loamy texture of
the soil and the infiltration of groundwater at this location meant that
the bed had to be underlined with bentonite-impregnated geotextile
material.
- A 150m
section of the right bank of the Boona Main Supply Channel near the town
industrial area was re-lined with clay.
Table 14.1 shows a summary of seepage
investigations and treatments since 1993/94.
Treatments carried out in 2000/2001 include works carried out during the
2001 winter maintenance program.
Table 14.1
Summary of seepage investigations and treatments since 1993/1994
It is possible to make an estimation of the water losses
saved by clay lining works undertaken this year by way of making several
assumptions:
- The
Idaho testing locations along the channel can be averaged over the whole
section of channel being clay-lined
- Prior
to clay lining, an average infiltration rate of 25mm/day is observed
- After
clay lining, an average infiltration rate of one mm/day is observed
- The
area over which infiltration occurs is the wetted perimeter of the channel
section multiplied by the length of channel
- The
average duration for which channels are full of water is 270 days/year
Using these assumptions it is estimated that the 2001 clay
lining and bank reconstruction of 4,975m2 wetted perimeter would
equate to one kilometre of channel and would save approximately 20 ML/year.
The results of the clay lining are consistent with the
projections of SKM seepage investigations.
These indicated that the cost of seepage reduction can not be justified
by the value of the water saved alone.
Most of this year’s remedial seepage work has revealed that
the identified seepage area is due to the bed of the channel intercepting a
“gypsum shot” soil layer. By preventing water entering this layer there should
be a change in the visible symptoms of the seepage. This may be a drying-up of
an area of swampy ground beside the channel, reduction in damage to roads
beside channels or the containment of the spread of salt-affected patches
beside channels. These identifiable
improvements are in addition to the area-wide reduced accessions to the
watertable that are achieved by seepage reductions.