6.6 Modifications
to infrastructure
The following modifications to assets have changed the
descriptions of the assets, but have not changed their functions.
The pipe culvert that takes Boona 7 Supply Channel under
Kidman Way was lengthened to improve traffic manoeuvrability at the
intersection with Jimmy Cull Road.
Coleambally 2 Supply Channel was fitted with two constant
level flow regulators. This channel
supplies water to horticultural blocks, and the installations will reduce
escape flows.
6.6.1 Commissioning
of new bridge and demolition of the old bridge
The new bridge over the Main Canal was completed and opened
to traffic. The old bridge is due to be demolished in winter 2002.

Plate 6.1 Completed Sturt Highway bridge over the Main
Canal
6.6.2 Installation
of flow meters to monitor deliveries to farms
On large area farms, CICL services 693 delivery points. Up to January 2001, CICL had installed 117
flow meters. These flow meters are of
three types; 95 propeller meters (by Tempress & McCrometer), 36 of two
types of ultrasonic flow meters (by MACE) and seven Irriflow® magnetic
induction meters (by Tyco).
In the 2001 winter maintenance program, no dethridge wheels
were replaced with flow meters. By
October a new flow-measuring device will be put on trial in five
locations. The flume gate by Rubicon
Systems is designed to fit into the existing body of the dethridge wheel. It records flow electronically, is radio
controlled and adjusts its flow automatically.
6.6.3 Original
long section design levels
The extension of the AHD levels through the CIA by the
Surveyor-Generals Department and the subsequent surveying of assets associated
with Whole Farm Planning has indicated that differences exist between the
original long section supply channel levels and the present levels of supply
infrastructure. Investigation of the effects of these differences using flow modelling
is continuing. Rationalisation of assets may be required.
|